West Plains City Council approves over $5 million in construction projects
Tue, 03/10/2026 - 12:58pm
admin
By:
Laura Wagner, contributing writer
In a special meeting held Wednesday, March 4, the West Plains City Council approved the reconstruction of Fire Station #3 and the construction services of SBI for the Provalus Project.
The city bid out the post remediation reconstruction project on Fire Station #3 after the mold remediation was completed. Two bids were received by the city with Koon Construction winning project at a cost of $35,949.13.
Moving on to the Provalus Project at 601 Washington Street, Councilman Ron Grennan recused himself from the discussion and voting. The city received three bids, and the construction contract was awarded to Springfield Builders Incorporated (SBI). The other two bidders were Killian Construction and Adams Construction. The winning low bid came in at a total cost of $5,166.612. Funding for the project will come from the U.S. Economic Development Administration (EDA) covering $1,501,373, the Missouri Department of Economic Development (MoDED) covering $2,500,000, and an additional match of $1,202,306. The city will face a gap of around $900,000 in funding for the Provalus Project.
Mayor Mike Topliff asked Finance Director Earlene Rich, "If worst comes to worst, what's our plan B in paying for this?"
Rich went on to explain that the city has the cash, but the question is from which funds the money should come. "We can do an interfund loan and pay it back by 2028/2029 when revenue is expected to come in."
With construction efforts being focused on the first floor and Mayor Topliff looking at the amount of jobs this could bring to West Plains, the city moved forward on the project focusing on the future return on investment.